Modules Summary April 2025
CMU has produced the first v3c Ti modules! Fifteen modules where produced and 14/15 are high quality (one has ohmic IV curve). Half of them are being sent to the Cassette Assembly Facility in Fermilab and the rest will remain in CMU for testing. CMU has now received all of the final tooling. It has been assembled and installed and is in the process of being commissioned. This will allow us to proceed at a cadence of four modules per day in May. We have hired a new technician who will start May 1st.
UCSB has make a run of fifteen HGCROC V3B HD Full modules; 14/15 of fifteen show are high quality (one has large placement offset). UCSB has inspected and shipped the last of the final gantry tooling to CMU and TTU. The final tooling for UCSB is expected soon and will be installed and commissioned when available.
Follow-ups
Links: